Ro-Pax ship “Colorline Hybrid”

Dedicated Customer Teams & Agile Services

Our worldwide presence ensures the timeliness, cost efficiency compliance adherence required to ensure your production timelines are met.

SCOPE:

  • Shop area
  • Public area and stairs

DURATION:

  • 14 months

WORKERS:

  • ~90

WORKS DONE:

  • Installation of wall & ceiling panels
  • Walls and top covering 9.000 m2
  • Ceiling with decorative elements 7.900 m2
  • Floors (floating, leveling, top covering)
  • Floating floor 1.500 m2
  • Vinyl floor top covering 3.600 m2
  • Carpet top covering 2.300 m2
  • Tiling works 500 m2
  • Insulation works 13.500 m2