Cruise ship “MSC Virtuosa”

Dedicated Customer Teams & Agile Services

Our worldwide presence ensures the timeliness, cost efficiency compliance adherence required to ensure your production timelines are met.

SCOPE:

  • 825 Cabins + corridor area
  • HVAC & Piping

DURATION: 12 months

WORKERS: ~50

WORKS DONE:

  • 1,3 kilometers +GF+ pipe installation
  • 300 units equipment installation
  • 54 tons of rectangular ducts installation
  • 2,5 kilometers of circular ducts installation
  • 1956 cabins and 198 lockers backside connections
  • Installation of wall & ceiling panels
  • Floors (floating, leveling, top covering)
  • Insulation works
  • Furniture installation