Cruise ship “MSC Bellissima”
Dedicated Customer Teams & Agile Services
Our worldwide presence ensures the timeliness, cost efficiency compliance adherence required to ensure your production timelines are met.
SCOPE:
- 825 Cabins + corridor area
- HVAC & Piping
DURATION: 12 months
WORKERS: ~50
WORKS DONE:
- 1,3 kilometers +GF+ pipe installation.
- 300 units equipment installation
- 43 tons of rectangular ducts installation
- 1 kilometer of circular ducts installation
- 1945 cabins and 198 lockers backside connections
- Installation of wall & ceiling panels
- Floors (floating, leveling, top covering)
- Insulation works